Temporary Closures of rights of way are usually to allow works to take place, for example, helicopter stonelifts for Fix the Fells work or replacement of large bridges. They may also be made for reasons of public safety, for example motor rallies, forestry, utility works or building works that affect public paths. Orders are planned in advance, and can last up to six months. Notices are for very short term issues and come into effect immediately.
A longer term Traffic Regulation Order is a legal order regulating traffic on public highways. This includes footpaths, bridleways, byways, restricted byways and carriageways with a predominantly unsealed surface. They can be made for reasons such as:
They can restrict:
If you have any queries, or wish to apply for a closure, please contact Nick Thorne; nick.thorne@lakedistrict.gov.uk or
Decisions to make traffic regulation orders are taken under delegated powers. Under the Openness of Government Regulations 2014 we publish all these decisions which can be seen on the Openness Of Government page.
There are a couple of regular motor rally events which necessitate the temporary closure of Rights of Way in forestry areas to ensure public safety each year; the Malcolm Wilson Rally (usually held on a weekend in early March) and the Grizedale Stages Rally (usually held on a weekend in early December).
There are two sets of information below:
Before we make an Order we have to tell people what we intend to do and why. These Notices of Intention are published in the local press and on this website at least 7 days before the Order is made.
Date of change: 21 November 2024
Following damage during Storm Arwen and subsequent rockfalls, the footpath to the lower falls at Stanley Ghyll has been closed by a Temporary Traffic Regulation Order because it has been damaged, made unstable, and unsafe - creating a danger to the public. The TTRO has been subsequently extended by the Secretary of State several times, and will currently expire on 1 June 2025. The section closed is between the former location of the footbridge (which has been removed) at SD 1742 9958 and the lower falls at SD 1743 9953. There is no access to the lower falls, but the upper falls are now visible from the viewing platform.
Our contractors have produced a report on remedial options for works which may reduce the risk from rockfall and other hazards. The site is a SSSI and Natural England consider that these remedial options would present an unacceptable detriment to the features of the SSSI.
We are therefore now considering making a (long-term) Traffic Regulation Order closing the affected section of footpath whilst the likelihood of danger to the public remains and we consider what other options may be available, and if further options can be identified allow us to assess, get consent for and carry out these works to reinstate the footpath. We would be grateful to receive any comments, representations or objections to such an order by Wednesday 18 December 2024 which you would like taken into account. Any such responses can be sent to will.hinchliffe@lakedistrict.gov.uk or in writing to: Rights of Way, LDNPA, Wayfaring House, Murley Moss, Oxenholme Road, Kendal, LA9 7RL.
PLEASE DO NOT ATTEMPT TO REACH THE BASE OF THE FALLS
Notice, TTRO Extension Letter, Order and Plan
Remove from website: 18 December 2025
Date of change: 15 November 2024
Westmorland and Furness Council made an Order in June 2023 closing the section of bridleways 342017 and 305007 over the bridge over the River Lowther at Whale, the bridge requires re-decking. The Order has been extended by the Secretary of State in November 2024 until the end of September 2025 or until the completion of works to repair the bridge (whichever is the earlier). Although the Order remains in effect, it will only be in force and the bridge unavailable to users during the works. The works are now expected to be completed during the Summer of 2025 and to take around 5 days. There will be no suitable alternative route during the works.
Extension Letter, Notice and Plan
Expires 30 September 2025
Date of change: 14 November 2024
We have made an Order to temporarily close rights of way to all traffic within the forests because of danger to the public from fast moving vehicles during motor rally events.
The forest paths and roads will be closed to all public access during the Grizedale Stages and Malcolm Wilson Rallies. The paths affected are:
Saturday 7 December 2024 - Grizedale West and Grizedale East
Friday 7 March 2025 - Wythop Woods (from 12:00)
Saturday 8 March 2025 - Grizedale West, Wythop Woods and Whinlatter Forest
Although the Order duration is for 6 months, it will only be in effect on the three days stated above. At other times the paths will be available as usual.
Site Notices, Notice and Order
Date of change: 23 October 2024
We have converted the previous 21-day emergency closure notice to a temporary closure order for the part of the footpath that runs immediately alongside the western end of Rusland Church - masonry has fallen from the tower and there appears a likelihood that more might fall before repair works can be undertaken to make it stable – posing an obvious risk to the public. Alternative routes are available passing through the churchyard around the eastern end of the church using the unaffected sections of the footpath and other paths within the churchyard.
The order will take effect from 23 October 2024 (when the current notice expires) and will continue in force for six months, or until works to stabilise the masonry have progressed such that it is safe to use the affected section of the footpath again, whichever is the earlier. If works to mitigate the danger have not sufficiently progressed during the order period, it may be extended with the authorisation of the Secretary of State.
Expires: 23 April 2025
Date of change: 10 October 2024
Forestry England (FE) have been issued a Statutory Plant Health Notice to control the spread of Phytophthora ramorum in larch within the Ling Mell / Silver Cove forestry plantations which requires them to fell and extract trees in the vicinity of footpath 407042. The only extraction route available to FE is via footpath 407042 so the surface will be disturbed during the works, along with machinery and vehicles operating on or beside the path. We have therefore made an order temporarily closing the affected section of the footpath (shown between points A and B on the plan). This comes into force on 21 October 2024. The order will last 6 months, or until works are complete, whichever is the earlier, and may be extended with the authorisation of the Secretary of State. Alternative routes are available via a forest track between points C and D (continuing on to or from Footpath 407036). For routes heading to or from Tewit How, it is possible to use Bridleway 407028 between points A-E-F (with banks persons operating between points A and E). An Order diverting the definitive lines of several rights of way including footpath 407042 and bridleway 407028 has recently been confirmed by the Planning Inspectorate 5 September 2024 - the order plan shows the new definitive lines.
Expires: 21 April 2025
Date of change: 9 October 2024
Forestry England (FE) have been issued a Statutory Plant Health Notice to control the spread of Phytophthora ramorum in larch within the Broadmoor forestry plantation, requiring them to fell and extract trees in the vicinity of bridleway 407067. The bridleway is within the risk zone for falling trees, we have therefore made an order temporarily closing the bridleway during the works. This will come into force when works begin. The order will last 6 months, or until works are complete, whichever is the earlier, and may be extended with the authorisation of the Secretary of State. The works are anticipated to take around 12 weeks once started. FE intend to make the bridleway safe before weekends and bank holidays so that the route can be available to the public at these times - signage on site will indicate when the bridleway is open or closed. An alternative route for cyclists and equestrian users will be available via the sealed U-road (U4277), footpath 407007 (Sawdust Lonning - which is also tarmacked and used as a vehicular road) and a short section of restricted byway 407061 (shown on the plan between points A-D-E-C). There is no suitable alternative for pedestrians.
Expires: 9 April 2025
Date of change: 16 September 2024
We have been issued a Statutory Plant Health Notice to control the spread of Phytophthora ramorum at Stanley Ghyll. To comply with this we must fell and extract affected larch trees in the vicinity of these footpaths. With the very steep and rough terrain there is a risk that trees felled adjacent to, or upslope of the footpaths, or rockfall, could unexpectedly fall across the footpaths endangering users. In places the footpaths will be the only safe, level ground from which contractors can feasibly carry out the work. We have therefore made an order temporarily closing the affected sections of the footpaths. This will come into effect when works begin. Work will be carried out on just one of the two possible routes shown on the plan between points A and B at any time, with the other route remaining open. Signage and fencing on site will indicate which route is closed and which can be used. An order may last up to six months but it is expected that the works will be completed during October, and the order will cease to be in effect once works are complete.
Order, Plan and Notice and Site Notice
Expires: 16 March 2025
Date of change: 5 September 2024
The Department for Transport has extended the Order temporarily closing sections of footpaths 513039 and 513040 whilst renovation works on the buildings at Beckside are carried out. The sections shown in red on the order plan between points A and C and points B and D will be closed until 28 March 2025, or until works which may endanger or obstruct the public are complete (if earlier). Alternative routes are available during the closure through the field to the south of the buildings - suggested routes are shown in green on the plan.
Site Notice and Extension Letter, Notice, Order and Plan
Expires: 28 March 2025
Date of change: 20 September 2024
The Department for Transport has extended the Order temporarily closing the railway footbridge and its approaches until 30 April 2025, or until the completion of the works, whichever is the earlier. Contractors working on behalf of Network Rail will be replacing corroded parts of the bridge structure and then replacing the decking, which was rotting. The order will remain in effect until the repairs are complete and the bridge safe to use. The works are now anticipated to be complete by the end of November 2024 once final designs are approved and the new metalwork fabricated (off-site) and installed.
An alternative route is possible from the south end of Main Street following bridleway 418029 along the beach and then footpath 418008 through the rail underpass to join footpath 418001 north through Walls Plantation. It should be noted that this route is not as accessible as the closed footpath and occasionally at high water this route may not be usable at all.
Site Notice, Extension Letter, Notice and Order
Expires: 30 April 2025 (or when works complete, if earlier)
Date of change: 17 July 2024
The Department for Transport has extended the Order temporarily closing this footpath where it crosses Cockmoss Bridge until 7 August 2025, or the completion of works to repair the bridge, whichever is the earlier. The abutment and parapet have been damaged and there is a danger that the bridge will collapse. The structure will need to be lifted out, repairs to the abutment made and a replacement bridge installed. The path will be closed over the bridge until works are complete. No alternative public right of way between Whitebeck and Moss Side exists other than the public roads (A5074/C5047).
Extension Letter, Notice, Order and Plan
Expires: 7 August 2025
Date of change: 24 July 2024
The Department for Transport has further extended the Order temporarily closing the bridleway between the A6 at Huck's Bridge (Low Borrowbridge) and Breast High Road, which has been affected by landslips, which are still deteriorating. The route is no longer safe for users on the original line of the bridleway. An alternative route exists adjacent to the closed path for walkers, but for cyclists and horse-riders the only alternative is the Breast High Road byway (ford) – which is sometimes impassable at the ford/stepping stones.
Extension Letter, Notice and Order
Expires: 3 September 2025
Date of change: 21 November 2024
Following damage during Storm Arwen and subsequent rockfalls, the footpath to the Lower Falls at Stanley Ghyll remains closed because it has been damaged, made unstable, and unsafe - creating a danger to the public. The section closed is between the former location of the footbridge (which has been removed) at SD 1742 9958 and the lower falls at SD 1743 9953. There is no access to the lower falls, but the upper falls are now visible from the new viewing platform.
The Secretary of State has now extended the order until 1 June 2025. Our contractors have produced a report on remedial options for works which may reduce the risk. The site is a SSSI and Natural England consider that these remedial options would present an unacceptable detriment to the features of the SSSI.
We are therefore now considering making a (long-term) Traffic Regulation Order closing the affected section of footpath whilst we consider what other options may be available, and if identified allow us to assess, get consent for and carry out these works to reinstate the footpath.
PLEASE DO NOT ATTEMPT TO REACH THE BASE OF THE FALLS
Notice, Extension Letter and Order- Stanley Ghyll Lower Falls, FP 408037- temporary closure
Expires: 1 June 2025
Date of change: 5 December 2023
Part of footpath 201023, along the bank of Newlands Beck south of Little Braithwaite (shown A-B in red on the attached plan) is closed to the public because the river washed away the bank and footpath during Storm Ciara (February 2020) with further subsequent damage. The extent of the damage has grown significantly since then.
The Order came into effect on 18 February 2020 and was extended until 31 December 2023 - the Secretary of State has now further extended this - until 31 December 2025. We intend to make a diversion order to resolve this issue. Meanwhile, please use alternative routes following public roads to the east or west and other footpaths, which can be seen on the map.
Case Officer: If you have any queries, please contact Nick Thorne, Senior Rights of Way Officer on 01539 792621 or nick.thorne@lakedistrict.gov.uk
Notice, Order and Extension Approval Letter- Newlands Beck, part of Footpath 201023
Expires: 31 December 2025
We need at least 10 weeks notice to process a Temporary Closure Order. Notices for 5 or 21 days can be processed immediately as we do not have to advertise them in the press. Costs of orders and notices are usually met by the applicant.
Please contact either your local Ranger of a member of the Ranger Service on
Sometimes it is necessary for us to remove or tape off an unsafe bridge, or rights of way become obstructed or difficult to use due to other issues such as stepping stones being washed away or a riverside path surface eroding or collapsing. These issues do not always necessitate a legal temporary closure if there is no danger to the public present. Below are locations with current issues we are aware of. We have provided details of usable alternatives where possible and what action will be taken to address the issues.
Location: Grid reference: NY 1109 2456, nearby What 3 Words reference: journals.concluded.homes
Details of issue: We have removed the bridge at Beech Hill as the beam had become rotten and was potentially unsafe.
Alternative routes: Possible alternatives on the surrounding road and rights of way network include the U2196 between Beech Hill and Mosser Mains or Footpath 209016 and 209002 between Beech Hill and Mosser Mains via Underwood, as shown on the map below.
Plans to address issue: We intend to replace this bridge over the Summer of 2024
No results have been found
Location: Grid reference: NY1970 1208, nearby What 3 Words reference: stint.brink.roses
Details of issue: We have removed the bridge over the River Liza on Bridleway 407001, to the southeast of Black Sail Hut as the bridge had sustained weather damage over the Winter and had started to deteriorate.
Alternative routes: The river can be forded at various locations when not in spate (including via a forestry track to the west), but please take care if doing so. The closest alternative bridge crossing for footpath users is via the footbridge on Footpath 407033, approximately 1 1/2 miles west-northwest, then following footpaths 407032 via Pillar Rock and east via Looking Stead (footpath 419035) to the top of Black Sail pass. Please note that this is a rough fell path.
Plans to address issue: We intend to replace the bridge near Black Sail hut over the Summer of 2024.
No results have been found