Temporary Closures of rights of way are usually to allow works to take place, for example, helicopter stonelifts for Fix the Fells work or replacement of large bridges. They may also be made for reasons of public safety, for example motor rallies, forestry, utility works or building works that affect public paths. Orders are planned in advance, and can last up to six months. Notices are for very short term issues and come into effect immediately.
A longer term Traffic Regulation Order is a legal order regulating traffic on public highways. This includes footpaths, bridleways, byways, restricted byways and carriageways with a predominantly unsealed surface. They can be made for reasons such as:
They can restrict:
If you have any queries, or wish to apply for a closure, please contact Nick Thorne; nick.thorne@lakedistrict.gov.uk or
Decisions to make traffic regulation orders are taken under delegated powers. Under the Openness of Government Regulations 2014 we publish all these decisions which can be seen on the Openness Of Government page.
There are a couple of regular motor rally events which necessitate the temporary closure of Rights of Way in forestry areas to ensure public safety each year; the Malcolm Wilson Rally (usually held on a weekend in early March) and the Grizedale Stages Rally (usually held on a weekend in early December).
There are two sets of information below:
Before we make an Order we have to tell people what we intend to do and why. These Notices of Intention are published in the local press and on this website at least 7 days before the Order is made.
PATH CLOSURE NOTICE
ROAD TRAFFIC REGULATION ACT 1984
THE LAKE DISTRICT NATIONAL PARK AUTHORITY
PART OF FOOTPATH 201058, BRAITHWAITE, ABOVE DERWENT PARISH
Date of change: 16 September 2024
Footpath 201058 is closed between NY 2316 2366 and NY 2318 2360 (Royal Oak to Croft Terrace) because of works being undertaken to remove rotten electricity poles and live overhead cables which pose a risk to the public. Once removed a new underground cable will be installed.
The notice comes into effect on 16 September 2024 and will continue in force for 5 days.
There is no suitable alternative route.
Date of change: 16 September 2024
We have been issued a Statutory Plant Health Notice to control the spread of Phytophthora ramorum at Stanley Ghyll. To comply with this we must fell and extract affected larch trees in the vicinity of these footpaths. With the very steep and rough terrain there is a risk that trees felled adjacent to, or upslope of the footpaths, or rockfall, could unexpectedly fall across the footpaths endangering users. In places the footpaths will be the only safe, level ground from which contractors can feasibly carry out the work. We have therefore made an order temporarily closing the affected sections of the footpaths. This will come into effect when works begin. Work will be carried out on just one of the two possible routes shown on the plan between points A and B at any time, with the other route remaining open. Signage and fencing on site will indicate which route is closed and which can be used. An order may last up to six months but it is expected that the works will be completed during October, and the order will cease to be in effect once works are complete.
Order, Plan and Notice and Site Notice
Expires: 16 March 2025
Date of change: 17 July 2024
We have made an Order temporarily prohibiting mechanically-propelled and animal-drawn vehicles from using Byway Open to All Traffic (BOAT) 584025. The surface has been affected by washouts and partial collapses. Our Ranger team intend to carry out work to repair or replace several of the drains, improve drain approaches and repair damaged sections of the surface. The BOAT will remain open to all other users. The order will come into effect on 1 August 2024. An order can last up to six months but it is anticipated that the works will be complete and the BOAT open to all users again by early September. For mechanically-propelled and animal-drawn vehicles the only possible alternative during the closure will be to use the surrounding road network.
Site Notice, Order, Notice and Plan
Expires: 1 February 2025
Date of change: 5 September 2024
The Department for Transport has extended the Order temporarily closing sections of footpaths 513039 and 513040 whilst renovation works on the buildings at Beckside are carried out. The sections shown in red on the order plan between points A and C and points B and D will be closed until 28 March 2025, or until works which may endanger or obstruct the public are complete (if earlier). Alternative routes are available during the closure through the field to the south of the buildings - suggested routes are shown in green on the plan.
Site Notice and Extension Letter, Notice, Order and Plan
Expires: 28 March
Date of change: 30 April 2024
We have converted the Notice temporarily closing the railway footbridge and its approaches into an Order (in effect from 30 April 2024). Contractors working on behalf of Network Rail are repairing and replacing corroded parts of the bridge structure and replacing the decking, which was rotting. This will remain in effect until 30 October 2024, or when the repairs are complete, whichever is earlier. The works are anticipated to be complete in July.
There are two possible alternative routes. From the south end of Main Street it is possible to follow bridleway 418029 along the beach and then footpath 418008 through the rail underpass to join footpath 418001 north through Walls Plantation. It should be noted that this route is not as accessible as the closed footpath and occasionally at high water this route may not be usable at all. Alternatively, the road tunnel under the railway on Main Street (north of the closed footbridge) can be used, please take care if using this as there is no footway through the tunnel.
Expires: 30 October 2024 (or when works complete, if earlier)
Date of change: 17 July 2024
The Department for Transport has extended the Order temporarily closing this footpath where it crosses Cockmoss Bridge until 7 August 2025, or the completion of works to repair the bridge, whichever is the earlier. The abutment and parapet have been damaged and there is a danger that the bridge will collapse. The structure will need to be lifted out, repairs to the abutment made and a replacement bridge installed. The path will be closed over the bridge until works are complete. No alternative public right of way between Whitebeck and Moss Side exists other than the public roads (A5074/C5047).
Extension Letter, Notice, Order and Plan
Expires: 7 August 2025
Date of change: 24 July 2024
The Department for Transport has further extended the Order temporarily closing the bridleway between the A6 at Huck's Bridge (Low Borrowbridge) and Breast High Road, which has been affected by landslips, which are still deteriorating. The route is no longer safe for users on the original line of the bridleway. An alternative route exists adjacent to the closed path for walkers, but for cyclists and horse-riders the only alternative is the Breast High Road byway (ford) – which is sometimes impassable at the ford/stepping stones.
Extension Letter, Notice and Order
Expires: 3 September 2025
Following damage during Storm Arwen and subsequent rockfalls, the footpath to the waterfall in Stanley Ghyll remains closed because it has been damaged, made unstable, and unsafe - creating a danger to the public. The section closed is between the bridge at SD 1742 9958 and the lower falls at SD 1743 9953. There is no access to the lower falls, but the upper falls are now visible from the new viewing platform.
We are currently investigating what we can do to rebuild / restore this path, and also making the rockface above it stable to minimise danger to the public. We don’t yet know what we can do, and so this may take some time.
PLEASE DO NOT ATTEMPT TO REACH THE BASE OF THE FALLS
All other rights of way in Stanley Ghyll are open, as is the viewing platform at the top of the site.
Notice, Extension Letter and Order- Stanley Ghyll Lower Falls, FP 408037- temporary closure
Expires: 1 December 2024
Date of change: 5 December 2023
Part of footpath 201023, along the bank of Newlands Beck south of Little Braithwaite (shown A-B in red on the attached plan) is closed to the public because the river washed away the bank and footpath during Storm Ciara (February 2020) with further subsequent damage. The extent of the damage has grown significantly since then.
The Order came into effect on 18 February 2020 and was extended until 31 December 2023 - the Secretary of State has now further extended this - until 31 December 2025. We intend to make a diversion order to resolve this issue. Meanwhile, please use alternative routes following public roads to the east or west and other footpaths, which can be seen on the map.
Case Officer: If you have any queries, please contact Nick Thorne, Senior Rights of Way Officer on 01539 792621 or nick.thorne@lakedistrict.gov.uk
Notice, Order and Extension Approval Letter- Newlands Beck, part of Footpath 201023
Expires: 31 December 2025
We need at least 10 weeks notice to process a Temporary Closure Order. Notices for 5 or 21 days can be processed immediately as we do not have to advertise them in the press. Costs of orders and notices are usually met by the applicant.
Please contact either your local Ranger of a member of the Ranger Service on
Sometimes it is necessary for us to remove or tape off an unsafe bridge, or rights of way become obstructed or difficult to use due to other issues such as stepping stones being washed away or a riverside path surface eroding or collapsing. These issues do not always necessitate a legal temporary closure if there is no danger to the public present. Below are locations with current issues we are aware of. We have provided details of usable alternatives where possible and what action will be taken to address the issues.
Location: Grid reference: NY 1109 2456, nearby What 3 Words reference: journals.concluded.homes
Details of issue: We have removed the bridge at Beech Hill as the beam had become rotten and was potentially unsafe.
Alternative routes: Possible alternatives on the surrounding road and rights of way network include the U2196 between Beech Hill and Mosser Mains or Footpath 209016 and 209002 between Beech Hill and Mosser Mains via Underwood, as shown on the map below.
Plans to address issue: We intend to replace this bridge over the Summer of 2024
No results have been found
Location: Grid reference: NY1970 1208, nearby What 3 Words reference: stint.brink.roses
Details of issue: We have removed the bridge over the River Liza on Bridleway 407001, to the southeast of Black Sail Hut as the bridge had sustained weather damage over the Winter and had started to deteriorate.
Alternative routes: The river can be forded at various locations when not in spate (including via a forestry track to the west), but please take care if doing so. The closest alternative bridge crossing for footpath users is via the footbridge on Footpath 407033, approximately 1 1/2 miles west-northwest, then following footpaths 407032 via Pillar Rock and east via Looking Stead (footpath 419035) to the top of Black Sail pass. Please note that this is a rough fell path.
Plans to address issue: We intend to replace the bridge near Black Sail hut over the Summer of 2024.
No results have been found